How to correctly install a heat exchanger device
The installation of a heat exchanger can significantly affect its operation. During installation, it is essential to prevent the machine from sinking or the pipes from undergoing excessive deformation, which could be transmitted to the connecting pipes of the heat exchanger
There are generally two types of bases for heat exchangers. One is a brick-built saddle-shaped base. On the equipment, there is no saddle-type support, but it is directly placed on the saddle-shaped base. If the equipment is not properly fixed, it may move due to thermal expansion. The other is a concrete base, where the heat exchanger equipment uses a saddle-type support to quickly fix it to the base
Before preparing for installation, it is essential to conduct a rigorous inspection of the foundation's quality. The main inspection focuses on its surface condition, elevation, plane position, shape, dimensions, and whether the reserved holes meet the actual needs. In addition, it is also necessary to check the threaded bolts of the equipment and ensure that all components are complete
After checking the base, it is necessary to place sizing blocks on it to make the equipment more stable. The area for placing the sizing blocks must be flat to ensure good contact between them. Additionally, the thickness of the sizing blocks can be adjusted according to actual needs to meet the design requirements
After that, use a level gauge to level the equipment, ensuring that all its connecting pipes can be connected without being stressed. Once leveled, the fabricated parts and the sizing blocks can be securely welded together. After aligning the equipment, secure it with anchor bolts, and then complete the installation of the heat exchanger on top
Additionally, when installing the heat exchanger, it is essential to consider future cleaning issues, ensuring ease of cleaning and facilitating future maintenance